Table 4.5.3.2.1. Site Infrastructure Requirements and Changes for Stockpile Management Alternatives at Pantex Plant
| Alternative | Electrical | Fuel | |||
|---|---|---|---|---|---|
| Energy (MWh/yr) | Peak Load (MWe) | Liquid (L/yr) | Gas (m3/yr) | Coal (t/yr) | |
| Current Resources (1994) |
|
13.6 2 | 1,775,720 | 14,600,000 3 | NA |
| No Action (2005) |
|
||||
| Total site requirement |
|
10 | 795,166 | 7,200,000 | NA |
| Change from current resources |
|
-3.6 | -980,554 | -7,400,000 | NA |
| Downsize Weapons Assembly/Disassembly and High Explosives Fabrication |
|
||||
| Total site requirement |
|
11 | 795,600 | 7,650,000 | NA |
| Change from No Action |
|
1 | 434 | 450,000 | NA |
| Downsize Weapons Assembly/Disassembly |
|
||||
| Total site requirement |
|
10 | 740,000 | 7,150,000 | NA |
| Change from No Action |
|
0 | -55,166 | -50,000 | NA |
| Phaseout Weapons Assembly/Disassembly and High Explosives Fabrication |
|
||||
| Total site requirement |
|
0 | 0 | 0 | NA |
| Change from No Action |
|
-10 | -795,166 | -7,200,000 | NA |